Project Accomplishments
• Performed a capacity analysis of two interceptor sewers to determine existing and future flows and existing capacity rights.
• Developed a set of alternatives to alleviate capacity issues within the BIS.
• Compiled a GIS database of existing project constraints (i.e. traffic, environmental, permits, etc...) and developed a constraints map.
• Developed screening criteria and an evaluation matrix to select the preferred alternative.
• Met the City’s aggressive project schedule of delivery of an alternatives memorandum by June 1, 2006.

|