IEC is provided construction management services to the County of San Diego Public Works Department for the rehabilitation of Gillespie Field's runway 9/27-R.

The project included mill and overway of runway 9/27-R, relocation of existing perimeter road, relocation of existing sewer line, demolition of existing drainage swale and placing new swale with a box culvert, enlarging fillets at the south end of runway 35, and relocating existing signage and lighting. This project was complete in July 2005.


View of finished runway and project, from high above runway 9/27R.

 

Gillespie Field welcome sign.

 

Paving P-401(AC) operation on runway 9/27-R.

• Construction Manager for entire project as county RER

• Project was completed on time and within budget

• FAA funded and accepted